As we have already informed, in April there was concluded the contract on delivery of painting products supposed for new building process of non-self-propelled barges pr. NBL-90.
Today the transshipment terminal of NIBULON received the first consignment of painting products.
For each barge there will be used 9300 litres of painting products. In particular, sheet and section metal will undergo processing with the following priming with zinc- silicate shop primer 15-20mkm thick. Wares of hull and electro-bench saturation that are installed on open parts undergo hot zincifying with the following priming with epoxy prime 50kmk thick.
All painting products meet the requirements of the corresponding standards.