During the New Year and Christmas holidays works on the implementation of shipbuilding orders of “NIBULON” have not been stopped. For such a short period a lot of work has been done. You can reassure yourself, looking at photos on the status of the construction.
So, now the construction of the last two (serial number 169, 170) out of 16 vessels heads into the homestretch, contracts on the construction of these vessels were signed on the 6th of March, 2009, and the construction of the next eight non-self-propelled vessels has been started with serial numbers 175-182 (in accordance with the contract signed on December 3, 2009).
Orders NoNo 169-170: painting works are being continued, electrical installation works have been started.
Orders NoNo 175-182: metal cutting is being performed; cutting of parts congestion is being finished. For orders NoNo 175-176 metal cutting and renting have already been started.