The contracting organizations specialized in assembly of metalware have already mounted six silos with a total capacity of 43 thousand tons, waste bins, upper and lower loading galleries. There have already been installed lighting on the upper and lower galleries.
The specialists also finish plating the headhouse with metalware. They have plated more than 30 m out of 47 m.
The pre-commissioning works, as well as improvement works, are in full swing at the construction site; in particular, the specialists are constructing roads and pouring the joints between foundations and silos.
Regarding the cargo berth reconstruction, all grooves have been rammed; the specialists have concreted the bottom of the sections 10 and 11. All the works to construct the cargo berth will have been finished by March 20.