To date, the specialists finish mounting the first silos at NIBULON’s construction site (15-16). Two more silos (14 and 17) are being mounted. The builders have started concreting foundations for the last two silos (18 and 19). All supports have been mounted for the installation of the upper gallery except bridges for silos 18 and 19. 70% of the storm water sewer has been laid, as well as 50 % of fire extinguishing routes have been laid. Installation of electrical equipment of the underground gallery has begun. The specialists are laying cables and installing equipment in the headhouse. The plate of the section No. 10 is being reinforced at the berth.
As noted earlier, the commissioning of the new complex for shipment of grain and oilseeds will enable the transshipment terminal to store seven crops separately and simultaneously. In addition, the terminal will be capable of receiving all crops during a marketing year and ensuring uninterrupted transportation of agricultural products along the Southern Buh River.