Rush Period for Ironworkers at “Voznesens’ka” Branch Construction Site

Despite the beginning of May holidays, the construction workers decided not to decrease pace of construction, gradually finishing main construction works.

Having examined the construction site, Sergiy Besedin, NIBULON’s deputy general director of capital construction, and heads from more than 20 construction organizations summarized that the construction works were performed according to schedule. On June 15, the transshipment terminal will normally receive agricultural commodities.
Thus, the ironworkers are the busiest ones at present.
Astarta Mlynelevatorbud  Ltd. will start constructing a ramp and side walls of the truck-tipper in the near future.  
The specialists from Transvit private company are finishing the first foundation intended for assembling a grain dryer.
In the middle of May, Construction Company Ltd. will mount the headhouse frame.
PDSP-10 Ltd will mount all the bucket elevator supports.
The workers have started to mount first metalware in the grain storage foundation axes. Poltavaspetsmontazh Ltd, Montazhspetskonstruktsiya Ltd. are assembling metalware of the upper loading galleries. The specialists from Spetsmontazh Engineering Ltd. are ready to mount belt conveyers over grain storages.
In addition, TavriyaMonolitBud Ltd. completes constructing the administrative and laboratory building. The partition for the first floor and the roof will be built soon.
Maister MARK Maister Ltd. has started mounting ventilation in the building, Artil-Bud Ltd. – finishing work, and Atrium-Kom Ltd.  – electric installation.
At the same time, the construction workers from SMU-25 Ltd. will soon construct the mechanical workshop.
The specialists from Ukrdobrobut Ltd. and Shcherbyna self-employed individual are finishing the bottom construction of a fire tank and a fire pumping station, respectively.
The construction workers from DI KOR-BUD Ltd. will soon construct walls of the terminal’s cafeteria and the roof.
The specialists have started finishing work inside the weighing station (Zhytlorembud-Nika), and Bulat Ltd. is preparing to install scales.
The workers have already started to construct a parking lot in the terminal’s territory.

Keep up with the latest news!

You will receive our news in a weekly digest format

[pwf_filter id="8699"]

Оформити заявку

Become a supplier

BECOME A LANDHOLDER

Order a service

Best Employer of the Year in the Socially Responsible Employer nomination
Issued by

All-Ukrainian Public Organization “Taxpayers Association of Ukraine”

Certifications

ISO 14001:2015

Year

2017, 2019

Андрій Вадатурський

CEO

Андрій Вадатурський став генеральним директором «НІБУЛОНу» після понад 15 років роботи в компанії — в липні 2022 року.

Він прийняв цю посаду після трагічної загибелі свого батька та засновника «НІБУЛОНу» Олексія Вадатурського разом із матір’ю Раїсою Вадатурською під час російського ракетного удару по їхньому дому в Миколаєві.

З 2014 до 2019 рік був народним депутатом України від одномандатного округу в Миколаївській області та членом Комітету з питань аграрної політики. У 2017 році створив і очолив велику міжпартійну групу, яка виступала за розвиток українських річок як транспортного засобу.  

Має ступінь магістра електротехніки Українського державного морського технічного університету та ступінь магістра економіки промисловості Лондонської школи економіки. У 2009 році за вагомий внесок у розвиток агропромислового комплексу України був нагороджений Президентом України, йому присвоєно звання «Заслужений працівник сільського господарства».

Одружений, має трьох дітей.

Send resume