Assembly of Strength Hulls on the Tugs of 121 Project will be Finished Soon

Another week of construction of three tugs of 121 project brought unfavourable weather conditions: sharp decrease of air temperature, rime, snow. But it does not influence production schedule having made only some changes in construction and caused increase of works at the workshops.
Thus, on berth, where the vessels’ hulls are placed, the work is in full swing. And we familiarize you with the construction progress.
At present welded outfitting has been approved; hull structures of sea chest and ice box have been tested; painting works have been started. Assembly of aft units of three tugs is being completed.
Besides, on the tugs there is being continued preparation for installation of diesel-generators to the room of auxiliaries and also jointing of aft edges.
Construction progress is in detail.
The first vessel of the project (manufacturing order 10003):
Unit No.13 (superstructure) has been assembled; welding works are being performed there. Units No.8 and 81 are being produced. Mounting of fender bar and installation of welded outfitting in the navigation room are being continued; ladders are being installed.
The second vessel of the project (manufacturing order 10004):
Assembly of unit No.4 (forebody) on the vessel’s hull is being completed. Assembly of units No.22 (navigation room) and No.13 (superstructure) will be finished soon. Besides, production of units No.8 and 81 has been started.
The third vessel of the project (manufacturing order 10005):
Preliminary works to prime outer part of fore half hull, namely straightening and dressing are being continued.
***
We would remind you that the company plans to build 12 non-self-propelled vessels of NBL-91 project, 12 shallow-draught tugs of 121 project, 35 self-propelled vessels of “Volgo-Don Max” type at its own shipyard.

Keep up with the latest news!

You will receive our news in a weekly digest format

[pwf_filter id="8699"]

Оформити заявку

Become a supplier

BECOME A LANDHOLDER

Order a service

Best Employer of the Year in the Socially Responsible Employer nomination
Issued by

All-Ukrainian Public Organization “Taxpayers Association of Ukraine”

Certifications

ISO 14001:2015

Year

2017, 2019

Андрій Вадатурський

CEO

Андрій Вадатурський став генеральним директором «НІБУЛОНу» після понад 15 років роботи в компанії — в липні 2022 року.

Він прийняв цю посаду після трагічної загибелі свого батька та засновника «НІБУЛОНу» Олексія Вадатурського разом із матір’ю Раїсою Вадатурською під час російського ракетного удару по їхньому дому в Миколаєві.

З 2014 до 2019 рік був народним депутатом України від одномандатного округу в Миколаївській області та членом Комітету з питань аграрної політики. У 2017 році створив і очолив велику міжпартійну групу, яка виступала за розвиток українських річок як транспортного засобу.  

Має ступінь магістра електротехніки Українського державного морського технічного університету та ступінь магістра економіки промисловості Лондонської школи економіки. У 2009 році за вагомий внесок у розвиток агропромислового комплексу України був нагороджений Президентом України, йому присвоєно звання «Заслужений працівник сільського господарства».

Одружений, має трьох дітей.

Send resume