We would remind you that the day of solemnities is announced as an open day. Everyone will be able to visit a solemn event and to see how the agrarian company NIBULON is reviving Ukraine’s shipbuilding sector now.
And now shipbuilding works are being continued.
NIBULON-5 (total readiness is 63,35 %):
1. Assembly and pipeline area: assembly of the main engines has been provided to a representative of the Shipping Register of Ukraine. The hoisting crane has been mounted; anchor and mooring single windlasses are being mounted. There is also being continued assembly of pipes of fire-fighting system, ballast system, drainage system, fuel system and assembly of pipes of sanitary systems: fresh water system, wash water system, sewage water system.
2. Painting area: decks of the vessel’s outer part are being painted; there is being performed gaining of paint thickness in the spaces of rudder-propeller complex, cofferdams and forepeak.
3. Area of mechanical and fitter’s items: final parts of guard railing are being produced; there is being manufactured an aft towing chock; production of ventilation pipes and air-conditioning pipes has been started.
4. Assembly and welding area: pre-insulation works are being continued; living accommodations are being prepared for insulation and plating. On the rudder-propellers there is being continued preparation for installation of galvanic protection and protection of propellers from mechanical damages.
5. The specialists of electrical area continue to lay cable in the tug’s engine room and in the living accommodations.