In 2018, NIBULON Shipbuilding and Repair Yard Plans to Launch Six Vessels and to Start the Construction of Three more Ones

NIBULON shipbuilding and repair yard in Mykolaiv successfully implements its shipbuilding program, as well as conducts repairs and performs maintenance of the vessels along with the reconstruction of the shipyard’s facilities. Director of NIBULON shipbuilding and repair yard Dmytro Horbenko told us about construction of the orders and scheduled loading of the shipyard in 2018 and in the first half of 2019.
The first non-self-propelled B5000 project vessel (101 m length) is being prepared for launching at the building berth. It should be noted that the vessel with such a length will be launched at the shipyard for the first time. It is possible thanks to reconstruction of the shipyard’s slipway, namely the construction of additional launching ways. At the moment of the acquisition of the property complex in August 2012 and creation of NIBULON shipbuilding and repair yard it constructed vessels of 70 m.
“The shipbuilders are constructing the second B5000 project vessel that will be launched in April and two multipurpose tugs of 3,500 hp (T3500 project). In addition, NIBULON shipbuilding and repair yard plans to construct four POSS-115 project tugs (two of them will be put into operation in August and in September) and a floating crane in 2018. In total, we will launch six orders in 2018”, said Dmytro Horbenko.
The shipbuilders are conducting repairs and performing maintenance of the company’s fleet along with the construction of vessels. Dmytro Horbenko explains,
“The specialists are performing maintenance of NIBULON-1 tug. Then they will perform maintenance of the non-self-propelled NBL-008 vessel. Upon completion of these operations, we will be able to perform a long-awaited launching of the first 100-m B5000 project vessel on February 23”.
You can find more details about construction of the orders at NIBULON shipbuilding and repair yard in our review:
 
Nibulonivets-2
The mooring trials are being finished. Upon completion of all the trials, the vessel will be put into operation.
 
The first non-self-propelled B5000 project vessel (it will be launched on February 23, 2018)
The specialists finish painting the sides of the outer plating of the vessel’s forebody.
The shipbuilders are preparing for cleaning and painting of the upper deck.
The coamings of the hold are being equipped. The tracks for the hatch covers are being installed.
The hatch covers are being produced.
 
The second non-self-propelled B5000 project vessel (it will be launched in April 2018)
The last sections of the forebody are being produced in the assembly and fabrication workshop.
Three units of the vessel’s afterbody have been formed on the building berth.
 
The first and the second T3500 project tugs (they will be launched in May and in June 2018)
The shipbuilders continue metal cutting and bending in the metal processing workshop. The specialists are producing other sections in the assembly and fabrication workshop.
The foundations of main engines have been installed on the formed sections. 

Keep up with the latest news!

You will receive our news in a weekly digest format

[pwf_filter id="8699"]

Оформити заявку

Become a supplier

BECOME A LANDHOLDER

Order a service

Best Employer of the Year in the Socially Responsible Employer nomination
Issued by

All-Ukrainian Public Organization “Taxpayers Association of Ukraine”

Certifications

ISO 14001:2015

Year

2017, 2019

Андрій Вадатурський

CEO

Андрій Вадатурський став генеральним директором «НІБУЛОНу» після понад 15 років роботи в компанії — в липні 2022 року.

Він прийняв цю посаду після трагічної загибелі свого батька та засновника «НІБУЛОНу» Олексія Вадатурського разом із матір’ю Раїсою Вадатурською під час російського ракетного удару по їхньому дому в Миколаєві.

З 2014 до 2019 рік був народним депутатом України від одномандатного округу в Миколаївській області та членом Комітету з питань аграрної політики. У 2017 році створив і очолив велику міжпартійну групу, яка виступала за розвиток українських річок як транспортного засобу.  

Має ступінь магістра електротехніки Українського державного морського технічного університету та ступінь магістра економіки промисловості Лондонської школи економіки. У 2009 році за вагомий внесок у розвиток агропромислового комплексу України був нагороджений Президентом України, йому присвоєно звання «Заслужений працівник сільського господарства».

Одружений, має трьох дітей.

Send resume