Thus, in the middle of December 2015, the shipyard will complete pre-start works and move the floating crane to the shipyard pier for outfitting.
The shipbuilders are conducting outfitting works, namely:
– assembly of the vessel’s superstructure units (completed);
– assembly of leakage collection system, ballast system, exhaust system, bottom and side accessories system (completed);
– production of ship’s ramp to be used for crane’s getting in and out of Terex Fuchs MHL 385 D grab mobile crane (in the process of completion);
– installation of pre-insulation welding equipment (in the process of completion);
– mounting of sewage system, system of air, sounding and overflow pipes, water based fire-fighting system, drainage system (in the process of completion);
– painting of ballast tanks (in the process of completion);
– painting of vessel’s spaces (in the process);
– installation of doors, portholes, ladders (in the process);
– preparation of anchor gears (in the process);
– installation of deck equipment, in particular reels, bitts, aft anchor-mooring capstans, anchors and anchor chains (in the process);
– installation of equipment in the superstructure and engine room (in the process);
– mounting of mechanical and fitter’s items in the open areas (in the process);
– approval of vessel’s spaces (in the process);
– mounting of spaces insulation (started);
– cleaning and painting of outer plating (started).
Upon completion of construction and launching, the vessel will receive the appropriate class of the Shipping Register of Ukraine: KE * Ice1 B-R4-RSN2,0 Industrial vessel.
Main dimensions: length – 38.5 m; breadth – 12 m; depth at midship – 3.45 m; draught – 1.45 m.