The specialists are producing and installing foundations for the propulsion unit (main engines and rudder propellers). They have laid decks of the unit No.11 (superstructure stern).
The first vessel of the project (manufacturing order 10003):
The unit No.12 (the superstructure midsection with living accommodations) has been installed; the shipbuilders are performing welding works. The lower living accommodations are being painted. The system pipelines are being produced and installed in the auxiliaries’ room.
The second vessel of the project (manufacturing order 10004):
NIBULON’s shipbuilders have installed the unit No.12; it is being mounted into the hull. Pre-insulation outfitting is being installed and welded in the lower living accommodations; the specialists prepare them for painting.
The third vessel of the project (manufacturing order 10005):
The unit No. 12 has been assembled and welded. The shipbuilders will mount it into the vessel’s hull. The unit No. 22 (pilot house) is being formed at the same time.