ALL ENGINEERING, a general contractor, has already assembled an elevator pit, a transitional underground gallery, and walls for a truck tipper’s pit. The contractor has installed foundations for four silos out of eight ones.
While Rembud Teremky Ltd. continues forming pile foundations for other units at NIBULON’s facility in Vinnytsia region, other contractors are assembling a pressure collector and framework metalware for the administrative and laboratory building’s units. The builders are constructing the railway line.
At the end of this week, the contractors plan to start assembling metalware of other important facility’s units, in particular an elevator tower and a truck tipper. The specialists will lay electric networks, construct fire tanks and foundations for a weighing station.
Please note that the proximity of agricultural producers from Vinnytsia and other regions to NIBULON’s new facility with the river capacity of 33.5 thousand tons will not only save the farmers’ means due to the reduction of transport expenses but also increase the profitability of their activity, as well as agricultural production in the region as a whole. Considering that NIBULON will transport all the grain from its new facility to its main terminal in Mykolaiv by railway, this will considerably remove trucks from Ukrainian roads. This is one of priority directions in the company’s activities.