The directors from eight contracting organizations involved in constructing at present reported on the construction progress achieved for the last week.
1. Perspectyva-Mykolayiv Ltd finished ramming piles intended for a truck-tipper. This organization completed the pile grating for the grain storage No.9 of 5.5 thousand tons.
2. Thus, the piles will soon be rammed at the construction site.
3. The workers are constructing the foundation for a headhouse, laboratory and administrative building, and workshop buildings.
4. The transformer substation has been significantly changed: the workers are installing double-gazed windows, doors and building the first floor.
5. A Volvo EC 700 CL hydraulic excavator purchased by NIBULON operates on the berth. Its grab volume (3.37 m3) and digging depth (more than 9 m) enable NIBULON itself to perform dredging near the berth and to conduct all excavation works at the construction site.
During the meeting, the company’s partners made up and corrected a work schedule to be performed in the near future. (All the contracting organizations must themselves organize safe work performance at the construction site).
1. VF VZAEMODIYA Ltd will start constructing the foundations for grain storages No. 7, 8, 9 at the beginning of April.
2. Chornomorgidrobud TDV VP BU 453 will have rammed all the piles for the grain storage No.12 by April 01. All the piles intended for the gallery for shipments on water transport will be rammed in a week.
3. Perspektyva-Mykolayiv Ltd will have rammed piles for a cafeteria as well as administrative and laboratory building by April 01.
4. It will take Kondratyuk V.S (an individual entrepreneur) less than two weeks in April to finish constructing the transformer substation.
5. TavriyaMonolitBud Ltd will have developed and presented a schedule of the administrative and laboratory building construction by April 02.
6. Transsvit private enterprise will have reinforced the bottom and walls of the grain-cleaning headhouse and also will have completed a foundation mattress for the grain storages No. 4, 5, 6 by April 02.
7. SMU-25 Ltd will have finished a zero cycle construction stage at the site till the beginning of April.
By the way, this very contracting organization has perfectly made an information board for a machine workshop. We suggest all the construction organizations following such an example of work organization.
Picture story about construction progress.