At SNC shipyard there are being completed assembly and welding works on intersectional and erection joints of the hull units (No10-40). The bow superstructure unit was mounted to the pontoon for further welding.
On the vessel there were placed a crane pillar (unit No70), an aft superstructure (unit No50), and a crane base. The crane pillar is being welded on.
Equipment is being installed on the vessel: water heating boiler, duct fans, emergency diesel-generator, emergency switchboard, and central air conditioner have already been placed.
Ballast system and sea-water cooling systems are being assembled in the engine room. Assembly of ventilation system has been started and is performed by Heinen & Hopman Engineering specialists.
There has been started installation of pipelines of drainage, fuel, and oil water systems.
Next week diesel-generators will be installed in the engine room.
Welded outfit is being installed in the floating crane units; guard railing and deck equipment are being assembled on the main deck.
Next week “Liebherr” crane will be placed on the vessel. The supplier’s representative has already arrived to the shipyard to conduct supervising installation. The vessel’s technical characteristics will allow to perform loading/unloading operations with wave height of up to 1.5 m and wind force of up to 20 m/s.