There is a photo report about status of St.Mykolai floating crane construction of NB 603 manufacturing order.
***
At present at the shipyard there is being performed hull formation in dry dock. In dry dock there have been placed two last sections of pressure-resistant hull: starboard section No40 (bow end) and port section No10 (aft end).
Starboard section No10 has been mounted to unit No20.
Romanian shipbuilders performed assembly work on erection joint between section No30 (central part) and unit No20. Welding is being continued now.
Other sections of the floating crane are being mounted actively.
On the shipyard working area there was completed welding of unit No90 (navigation house) and unit No60 (superstructure). Assembly of welded outfit and guard railing is being continued.
Assembly of equipment, electric and fitter items (cable paths) is performed in the engine room.
Deck equipment, electrical equipment, chains and anchors were delivered to the shipyard in full.
***
In April there will be performed a launching of the vessel to be fitted afloat.
After launching it will be equipped i.e. assembly of cable and pipeline fittings, outfit of galley and spaces, installation work, installation of electronics, navigation devices, engines and auxiliaries.