The flow and transport system, including high-productive conveyor and elevator equipment (up to 500 tons per hour) supplied by Buhler, has been installed and tested at the new elevator complex for shipment of grain and oilseeds built in the territory of NIBULON’s transshipment terminal in Mykolaiv. The above-mentioned system ensures not only the processes of internal movement of grain but also shipment on vessels.
The specialists have also assembled equipment in the headhouse. They are assembling a loading rack for water transport shipments.
Meanwhile, the specialists have already installed screws intended for removal of a residual cone of grain in silos. In addition, the grain storage capacities are equipped with devices to control grain moisture and temperature inside facilities remotely. It is important when ensuring agricultural commodity storage quality.
The weather conditions improved, and the territory improvement was renewed. In particular, access ways to the silos have been concreted. The specialists are preparing to concrete the rest of the territory of the new complex.
The cargo berth reconstruction is at the final stage. Ukrdobrobud (Kyiv) plans to finish the berth reconstruction by March 20. The specialists are finishing preparations for concreting of the upper deck of the 10th section of the berth. We would remind you that the berth reconstruction provides for its extension from 104 m to 222 m. Due to this, the length of waterside at the transshipment terminal will attain almost 800 m, thereby enabling us to handle up to five vessels simultaneously.